Once again Mother nature cooperated with Habitat for Humanity and provided us with a beautiful day.
A HUGE crew was on hand and an enormous amount of work was completed on Saturday.
The remaining interior walls leftover from last weekend were built, stood in place and braced.The gable end trusses were sheeted on the ground prior to being craned into place. All the roof trusses were set, braced and ready for roof sheeting. After lunch,we started installing the plywood on the roof while other volunteers installed blocking in the walls,finished up some misc. sheeting on the exterior walls and organized the job site '
Thanks to Gallop Concrete for supplying the crane to set the roof trusses on the house.
Next weeks agenda will be to install the rest of the roof sheeting and build the front porch deck.
Many thanks to all who helped. Keep up the great work!!