Knock on wood!!!! Habitat was once AGAIN blessed with some beautiful weather to continue work on our 20th build.
The ambitious and eager crew from BEST BUY was once again on site to contribute their time and effort to our build for Chris, Penny and Matt.
The siding was completed today and the house looks awesome!! This would not have been accomplished without the direction of our siding expert Bill Tretiak from Tretiak Construction of Corinth. Bill, we can't thank you enough.

The storage shed package was delivered and the majority of the shed is up and waiting for completion next weekend.
Front and rear railings were installed on the porches and a fresh coat of paint was applied to all the exterior doors while the weather was so cooperative.
During the week, Reddon Electric came in and completed roughing in of the electrical work.
And it just so happened, Pat (Reddon) stopped in today just in time for lunch!!!
Pat had heard that SUBWAY was once again supplying us with a delicious lunch. And best of all, they sent cookies!!!! Thank you Subway.

Next week we should start insulating the house and work will continue on the storage shed.

Once again a big "THANK YOU" to all our volunteers and the many companies that have donated or discounted their labor and material to help keep our project costs minimal.