Progress Update
Beautiful weather greeted the
crew working Saturday November 5. Demolition of the front porch was completed. Minor plumbing line
relocation was done while walls were open.

Speaking of walls, Matt and Mark framed new walls for the basement
stairs. These will add safety (fall
protection) as well as a sturdy place to mount handrails.
Mark and Mark dug and poured footings for
the new back porch.
Outside cleanup continued and new bathroom
fan/light units were installed, wired, and plumbed to vent outside. Matt and Nicole installed the shower and
installed moisture-resistant drywall.
Shout Outs
Thanks to Matt for spending his
Friday evening shopping for materials to help us get an early start on
Saturday.
Thanks to Hill Electric Supply in
Glens Falls for donating the materials needed to update the wiring, panel, and
smoke alarms in the house.
Thanks to Advanced Rental and Supply of Queensbury
for donating the use of a portable mixer and power auger.
Thanks to Matt and Nicole for
working on Sunday to install the shower and drywall!
What’s Coming Up
On Friday the 11th we
will welcome dozens of staff from Six Flags as they spend a day working on our
house. The roof will be stripped and
replaced, the siding will be power washed, new front and back porches will be
constructed, drywall repairs completed, walls washed and primed and floor
underlayment will be installed.
On Saturday, November 12 we will
host our ceremonial groundbreaking at 9:00am.